Bob Buescher Homes Custom Build Process

Step 1: Sign Agreement

Step 2: Make Selections

Step 3: Ground Breaking

  • Weeks 1-2: Excavation & Foundation (2 weeks)
  • Weeks 3-5: Framing (3 weeks)
  • Weeks 6-8: Mechanical Rough-in (3 weeks)
  • Weeks 9-11: Insulation & Drywall (3 weeks)
  • Weeks 12-15: Interior Trim & Paint (4 weeks)
  • Weeks 16-17: Hard Surface Flooring & Cabinets (2 week)
  • Weeks 18-21: Carpet & Cleaning (4 weeks)
  • Weeks 22-24: Final Walk-Through & Closing (3 weeks)

*Note: This is a general 24-week timeline – all homes may not fit this exact schedule. Most decisions are required prior to starting each house. All final interior details and color selections will be made by week six.