Our Building Process

building your home

Starting Point: Sign Contract
Weeks 1-2: Excavation & Foundation (2 weeks)
Weeks 3-4: Framing (2 weeks)
Weeks 5-7: Mechanical Rough-in (3 weeks)
Weeks 8-10: Insulation & Drywall (3 weeks)
Weeks 11-14: Interior Trim & Paint (4 weeks)
Week 15: Hard Surface Flooring & Cabinets (1 week)
Weeks 16-17: Carpet & Cleaning (2 weeks)
Week 18: Final Walk-Thru & Closing (1 week)

*Note: This is a general 18-week timeline - all homes may not fit this exact schedule.  You will be given your closing date when you sign a contract to build. Most decisions are required prior to starting each house. All final interior details and color selections will be made by week six.