| Starting Point: | Sign Contract |
| Weeks 1-2: | Excavation & Foundation (2 weeks) |
| Weeks 3-4: | Framing (2 weeks) |
| Weeks 5-7: | Mechanical Rough-in (3 weeks) |
| Weeks 8-10: | Insulation & Drywall (3 weeks) |
| Weeks 11-14: | Interior Trim & Paint (4 weeks) |
| Week 15: | Hard Surface Flooring & Cabinets (1 week |
| Weeks 16-17: | Carpet & Cleaning (2 weeks) |
| Week 18: | Final Walk-Thru & Closing (1 week) |
*Note: This is a general 18-week timeline - all homes may not fit this exact schedule. You will be given your closing date when you sign a contract to build. Most decisions are required prior to starting each house. All final interior details and color selections will be made by week six.